Calculate the 10% statutory construction lien holdback required on progress draws to protect against subcontractor liens, standard across most Canadian provinces.
The total agreed price for the construction or renovation.
The amount the contractor is currently billing you for work completed.
Statutory holdback is typically 10% in Ontario, BC, Alberta, etc.
GST/HST/PST applied to the progress draw.
Note: Holdbacks are typically released 45 to 60 days (depending on the province) after substantial completion, provided no construction liens have been registered against the property. Do not release holdback funds early. Taxes are calculated on the net draw (after holdback), and the holdback amount is taxed when it is finally released.
Calculate statutory lien holdbacks (typically 10%) and net contractor progress payments under Canadian provincial construction lien legislation.
Statutory 10% holdback requirements and substantial performance regulations in Ontario.
View official regulation →A builder submits a progress draw claim of $100,000 on a $500,000 custom home contract.
| Contract Value | $500,000.00 |
|---|---|
| Progress Claim | $100,000.00 |
| Statutory Holdback Rate | 10.0% |
| Progress Claim | $100,000.00 |
|---|---|
| Statutory Holdback Retained | $10,000.00 |
| Net Payment Due | $90,000.00 |